Aug 3, 2010

Draft Project Management Plan for 2010 Phase I Remedial Investigation Services Compliance Restoration Sites CC-RVAAP-78 and CC-RVAAP-80, Aug. 4, 2010

Final Work Plan for Sampling and Closure of Load Lines 1 -4, 12 (RVAAP- 08, 09, 10, 11, 12) and other Areas of Concern, July 30, 2010

Final Project Management Plan for Sampling and Closure of Load Lines 1 -4, 12 (RVAAP- 08, 09, 10, 11, 12) and other Areas of Concern, July 30, 2010

Final Quality Control Plan for the Revision of the Facility-Wide Environmental Documents, July 27, 2010

Draft Public Involvement Plan Addendum for Military Munitions Response Program Remedial Investigation Environmental Services, July 19, 2010

Final Facility-wide Groundwater Monitoring Program Report on the January 2010 Sampling Event, July 6, 2010

Draft Work Plan for the Military Munitions Response Program Remedial Investigations Environmental Services, July 6, 2010

Draft Project Management Plan for the 2010 Phase I Remedial Investigation Services at Compliance Restoration Sites (9 Areas of Concern), July 2, 2010

Draft Site Safety and Health Plan for the 2010 Phase I Remedial Investigation Service at Compliance Restoration Sites (9 Areas of Concern), Addendum No. 1, July 2, 2010

Final Quality Control Plan for the 2010 Phase I Remedial Investigation Services at Compliance Restoration Sites (9 Areas of Concern), July 2, 2010

Draft Data Quality Objectives Report for RVAAP- 05 Winklepeck Burning Grounds, Version 1.0, June 18, 2010

July 30, 2010

Final Facility-Wide Groundwater Monitoring Program Report on the 2009 Metals Sampling Event, Volume 1 - Main Text, Appendices A - C, June 2, 2010

Final Quality Control Plan for the Geochemical Evaluation of Metals in Groundwater, May 26, 2010

Draft Project Management Plan for Sampling and Closure of Load Lines 1 -4, 12 (RVAAP- 08, 09, 10, 11, 12) and other Areas of Concern, May 25, 2010

Draft Work Plan for Sampling and Closure of Load Lines 1 -4, 12 (RVAAP- 08, 09, 10, 11, 12) and other Areas of Concern, May 25, 2010

Operations and Maintenance Trip Reports and Quarterly Effectiveness Evaluation Reports Time Critical Response Action for the Rocket Ridge Area of Open Demolition Area #2 (RVAAP-004-R-01 Open Demolition Area #2 MRS) Trip Report #8, May 2010. May 24, 2010

Operations and Maintenance Quarterly Effectiveness Evaluation Report #1 for the Sand Creek Barrier, May 2010, May 24, 2010

Final Monitoring Report for the Deep Bedrock Well Installation in the Basal Sharon Conglomerate, May 21, 2010

Draft Facility-wide Groundwater Monitoring Program Report on the January 2010 Sampling Event, April 30, 2010

Operations and Maintenance Trip Reports and Quarterly Effectiveness Evaluation Reports Time Critical Response Action for the Rocket Ridge Area of Open Demolition Area #2 (RVAAP-004-R-01 Open Demolition Area #2 MRS) Trip Report #7, April 2010, April 29, 2010

Final Geophysical Prove-out Report for Environmental Services at RVAAP- 34 Sand Creek Disposal Road Landfill, RVAAP- 03 Open Demolition Area #1, And RVAAP- 28 Mustard Agent Burial Site, Version 1.0, March 25, 2010.

June 30, 2010 “Final Installation Action Plan Ravenna Army Ammunition Plant - FY 2009”  September 18, 2009
June 2, 2010

Final Public Involvement Plan Addendum for the Time Critical Removal Action at the Rocket Ridge Area, May 7, 2010

Final Project Work Plan for the Time Critical Removal Action (TCRA) at the Rocket Ridge Area (RRA) within RVAAP-004-R-01 Open Demolition Area #2 MRS, May 7, 2010

Final Project Management Plan for the Time Critical Removal Action (TCRA) at the Rocket Ridge Area (RRA) within RVAAP-004-R-01 Open Demolition Area #2 MRS, May 7, 2010

Operations and Maintenance Trip Reports and Quarterly Effectiveness Evaluation Reports Time Critical Response Action for the Rocket Ridge Area of Open Demolition Area #2 (RVAAP-004-R-01 Open Demolition Area #2 MRS) Trip Report #6, March, 2010

April 29, 2010

Final Facility-Wide Groundwater Monitoring Program Report on the October 2009 Sampling Event, Apr. 19, 2010

Draft Quality Control Plan for the Geochemical Evaluation of Metals in Groundwater, Apr. 12, 2010

Historical Archives - Official Publication of the Ravenna Ordnance Plant of Ohio, Volume 2, Number 5, May 1942

Historical Archives - Ravenna Ordnance Center Commissary Building (Bldg. 1038), APCO, Ohio, Post Card

March 29, 2010

Final Facility-Wide Human Health Cleanup Goals for Ravenna Army Ammunition Plant, Mar. 23, 2010

Draft Sampling and Analysis of Soils Below Floor Slabs at RVAAP- 08 Load Line 1 and Other Building Locations, Mar. 15, 2010

Historical Archives - Official Publication of the Ravenna Ordnance Plant of Ohio, Volume 3, Number 2, February 1943

Historical Archives - Official Publication of the Ravenna Ordnance Plant of Ohio, Volume 3, Number 1, January 1943

Historical Archives - Official Publication of the Ravenna Ordnance Plant of Ohio, Volume 2, Number 12, December 1942

Historical Archives - Official Publication of the Ravenna Ordnance Plant of Ohio, Volume 2, Number 2, February 1942

Historical Archives - Ravenna Ordnance Plant Manual of Safe Practices, Jan 1941

Mar. 15, 2010

Final Remedial Action Report for the RVAAP- 16 Fuze and Booster Quarry Landfill/Ponds. Mar. 5, 2010

Final Facility-Wide Groundwater Monitoring Program Annual Report for 2009, Mar 4, 2009

Draft Facility-Wide Groundwater Monitoring Program Report on the 2009 Metals Sampling Event, Volume 1 - Main Text, Appendices A - C
Mar. 2, 2010

Final Project Management Plan Performance-Based Acquisition for Six Environmental Areas of Concern, Revision 1, Mar. 1, 2010

Operations and Maintenance Trip Reports and Quarterly Effectiveness Evaluation Reports Time Critical Response Action for the Rocket Ridge Area of Open Demolition Area #2 (RVAAP-004-R-01 Open Demolition Area #2 MRS) Trip Report #5, February 2010, Feb. 18, 2010

Draft Facility-Wide Groundwater Monitoring Program Report on the October 2009 Sampling Event, Volume 1 - Main Text, Appendices A- D, Feb. 5, 2010

Feb. 23, 2010 Final Sampling and Analysis Plan Addendum No. 1 for Environmental Service at RVAAP- 34 Sand Creek Disposal Road Landfill, RVAAP- 03 Open Demolition Area #1, and RVAAP- 28 Mustard Agent Burial Site, Feb. 11, 2010.
Feb. 12, 2010

Draft Geophysical Prove-out Report for Environmental Services at RVAAP- 34 Sand Creek Disposal Road Landfill, RVAAP- 03 Open Demolition Area #1, And RVAAP- 28 Mustard Agent Burial Site, Version 1.0, Feb. 5, 2010

Operations and Maintenance Quarterly Effectiveness Evaluation Report #1 for the Sand Creek Barrier, January 2010, Feb. 1, 2010

Draft Project Work Plan for the Phase II Time Critical Removal Action (TCRA) at the Rocket Ridge Area (RRA) within RVAAP-004-R-01 Open Demolition Area #2 MRS, Jan 29, 2010

Draft Project Management Plan for the Phase II Time Critical Removal Action (TCRA) at the Rocket Ridge Area (RRA) within RVAAP-004-R-01 Open Demolition Area #2 MRS. Jan. 29, 2010

Draft Public Involvement Plan Addendum for the Phase II Time Critical Removal Action at the Rocket Ridge Area, Jan. 29, 2010

Operations and Maintenance Trip Reports and Quarterly Effectiveness Evaluation Reports Time Critical Response Action for the Rocket Ridge Area of Open Demolition Area #2 (RVAAP-004-R-01 Open Demolition Area #2 MRS), Trip Report #4, January 2010

Final Remedial Design for the RVAAP- 01 Ramsdell Quarry Landfill at Ravenna Army Ammunition Plant, Jan. 25, 2010

Final Facility-Wide Groundwater Monitoring Program Report on the July 2009 Sampling Event, Volume 1, Jan. 25, 2010

Draft Work Plan for the Geochemical Evaluation of Metals in Groundwater at Ravenna Army Ammunition Plant, Jan.14, 2010

Final PBA 2008 Supplemental Investigation Sampling and Analysis Plan Addendum No. 1 at Ravenna Army Ammunition Plant, Dec. 23, 2009

Operations and Maintenance Trip Reports and Quarterly Effectiveness Evaluation Reports Time Critical Response Action for the Rocket Ridge Area of Open Demolition Area #2 (RVAAP-004-R-01 Open Demolition Area #2 MRS), Trip Report #3, December 2009

Final Environmental Baseline Survey for the Ravenna Army Ammunition Plant, Sept. 25, 1998

Dec. 18, 2009

Final Removal Action Report for the Time Critical Removal Action (TCRA) at the Rocket Ridge Area (RRA) within RVAAP-004-R-01 Open Demolition Area #2 MRS, Dec. 17, 2009

Draft Faciilty-Wide Groundwater Monitoring Program Annual Report for 2009, Dec. 10, 2009

Operations and Maintenance Trip Reports and Quarterly Effectiveness Evaluation Reports Time Critical Response Action for the Rocket Ridge Area of Open Demolition Area #2 (RVAAP-004-R-01 Open Demolition Area #2 MRS), Trip Report #2, Nov. 24, 2009

Operations and Maintenance Trip Reports and Quarterly Effectiveness Evaluation Reports Time Critical Response Action for the Rocket Ridge Area of Open Demolition Area #2 (RVAAP-004-R-01 Open Demolition Area #2 MRS), Trip Report #1, Oct. 29, 2009

Dec. 10, 2009

Final Multi-Increment Sampling and Analysis of Soils Below Floor Slabs at RVAAP- 09 Load Line 2, RVAAP- 10 Load Line 3, and RVAAP- 11 Load Line 4 at Ravenna Army Ammunition Plant, Dec. 04, 2009

Draft Site Characterization and Focused Feasibility Study Work Plan for the RVAAP- 51 Dump Along Paris-Windham Road at Ravenna Army Ammunition Plant, Dec. 09, 2009

Nov. 30, 2009

Final Remedial Action Completion Report for RVAAP- 05 Winklepeck Burning Grounds Pads 61/61A, 67, and 70 at Ravenna Army Ammunition Plant, Nov 19, 2009

Draft Project Management Plan Performance-Based Acquisition for Six Environmental Areas of Concern, Revision 1 at Ravenna Army Ammunition Plant, Nov. 18, 2009

Final Data Quality Objectives Report for RVAAP- 03 Open Demolition Area #1 at Ravenna Army Ammunition Plant, Oct. 09, 2009

Final Construction Completion Report Time Critical Response Action for the Rocket Area of Open Demolition Area #2 (RVAAP-004-R-01 Open Demolition Area #2 MRS) Military Munitions Response Program, Sep. 23, 2008

Operations and Maintenance Trip Reports and Quarterly Effectiveness Evaluation Reports Time Critical Response Action for the Rocket Ridge Area of Open Demolition Area #2 (RVAAP-004-R-01 Open Demolition Area #2 MRS) August 2008 – September 2009, Aug. 26, 2008

Final Revised Operations and Maintenance Plan for the Sand Creek Barrier System, the Time Critical Response Action at the Rocket Ridge Area of Open Demolition Area #2 (RVAAP-004-R-01 Open Demolition Area #2 MRS) Military Munitions Response Program, Aug. 7, 2008

Final Time Critical Response Action Plan for the Rocket Ridge Area at Open Demolition Area #2 (RVAAP-004-R-01 Open Demolition Area #2 MRS) Military Munitions Response Program, Mar. 1, 2008

Final Work Plan for Sand Creek Survey Rocket Ridge Area of Open Demolition Area #2 (RVAAP-004-R-01 Open Demolition Area #2 MRS) Military Munitions Response Program Time Critical Response Action, Oct. 24, 2007

Nov. 18, 2009

Final Facility-Wide Groundwater Monitoring Program Report on the April 2009 Sampling Event, Volume 1, Appendices A - D, Nov 09, 2009

Draft Facility-Wide Groundwater Monitoring Program Report on the July 2009 Sampling Event, Volume 1, Nov 02, 2009

Draft Removal Action Report for the Time Critical Removal Action (TCRA) at the Rocket Ridge Area (RRA) within RVAAP-004-R-01 Open Demolition Area #2 MRS, Oct. 30, 2009

Final Safety, Health, and Emergency Response Plan for Environmental Services at RVAAP- 34 Sand Creek Disposal Road Landfill, RVAAP- 03 Open Demolition Area #1, and RVAAP- 28 Mustard Agent Burial Site, Oct. 14, 2009

Final Investigation of the Under Slab Soils Post Slab and Foundation Removal at RVAAP- 39 Load Lines 5, RVAAP- 40 Load Line 7, RVAAP- 41 Load Line 8, and RVAAP- 43 Load Line 10, Jan. 09, 2009

Final Sampling and Analysis Plan and the Site Safety and Health Plan for the Exposed Soil Sampling and Characterization After Slab and Foundation Removals at RVAAP-39 Load Line 5, RVAAP-40 Load Line 7, RVAAP-41 Load Line 8, and RVAAP-43 Load Line 10, Aug. 1, 2007

Oct. 18, 2009 Draft for the Remedial Design for the RVAAP- 01 Ramsdell Quarry Landfill at Ravenna Army Ammunition Plant, Oct. 13, 2009
Oct. 06, 2009

Remedial Design for RVAAP- 12 Load Line 12 at Ravenna Army Ammunition Plant, Oct. 1, 2009

Draft Feasibility Study for Groundwater at RVAAP- 12 Load Line 12 at Ravenna Army Ammunition Plant, Sept. 28, 2009

Draft Facility-Wide Groundwater Monitoring Program Metals Analysis Addendum, Sept. 10, 2009

Operations and Maintenance Quarterly Effectiveness Evaluation Reports (#4) and Barrier Repairs Time Critical Response Action for the Rocket Ridge Area of RVAAP-004-R-01 Open Demolition Area #2, Sept. 02, 2009

Sept. 28, 2009

Operations and Maintenance Trip Reports and Quarterly Effectiveness Evaluation Reports Time Critical Response Action for the Rocket Ridge Area of RVAAP- 04 Open Demolition Area #2, September Trip Report (#12), Sept. 2, 2009

Wetlands and Other Waters Delineation Report Remedial Action Areas at Ramsdell Quarry Landfill, Load Line 12, and Fuze and Booster Quarry Landfill/Ponds at the Ravenna Army Ammunition Plant and Ravenna Training and Logistics Site, Ravenna, Ohio. Dec. 29, 2008

Final Ravenna Army Ammunition Plant's Facility Wide Surface Water Assessment Workplan, Jan. 27, 2003

Sept. 17, 2009

Final Project Management Plan for 14 Military Munitions Response Program Areas of Concern at Ravenna Army Ammunition Plant, Sept 14, 2009

Final Work Plan Performance-Based Acquisition for Environmental Investigation and Remediation MEC Avoidance/Removal Services, Sept 09. 2009

Sept. 1, 2009 Final Project Completion Report for the Munitions Response for Demolition of Load Lines 5, 7, Building 1039, and Transite Removal at Building T-1604, Volume 1 Main Text and Appendices A-C, Dec 13, 2007
Aug 31, 2009

Draft of the Facility-Wide Groundwater Monitoring Program Report on the April 2009 Sampling Event, Aug. 21, 2009

Draft Data Quality Objectives Report for RVAAP- 03 Open Demolition Area #1 at Ravenna Army Ammunition Plant, Aug 6, 2009

Final Work Plan Addendum 1 for the Sampling of Soils Below Floor Slabs and Remediation at RVAAP- 08 Load Line 1 and Other Building Locations at Ravenna Army Ammunition Plant, Aug. 3, 2009

Final of the Facility-Wide Groundwater Monitoring Program Report on the January 2009 Sampling Event, July 31, 2009

Final Sampling and Analysis Plan for the Remedial Investigation of RVAAP- 67 Facility-wide Sewers Addendum No. 1 at Ravenna Army Ammunition Plant, July 31, 2009

Operations and Maintenance Trip Reports and Quarterly Effectiveness Evaluation Reports Time Critical Response Action for the Rocket Ridge Area of RVAAP- 04 Open Demolition Area #2, July Trip Report (#11), July 29, 2009

Addendum to the Final Site Safety and Health Plan, Time Critical Removal Action at the Rocket Ridge Are within RVAAP- 004-R-01 Open Demolition Area #2 MRS at Ravenna Army Ammunition Plant, July 17, 2009

Final Ravenna Army Ammunition Plant Facility Wide Ecological Risk Work Plan, April 21, 2003

 

July 22, 2009

Final Data Quality Objectives for the RVAAP- 34 Sand Creek Disposal Road Landfill at Ravenna Army Ammunition Plant, Version 1.0, July 16, 2009

Final Geophysical Investigation Plan for RVAAP- 34 Sand Creek Disposal Road Landfill, RVAAP- 03 Open Demolition Area #1 and RVAAP- 28 Mustard Agent Burial Site at Ravenna Army Ammunition Plant, Version 1.0, July 16, 2009

Draft Remedial Design for RVAAP- 12 Load Line 12 at Ravenna Army Ammunition Plant, July 13, 2009

Operations and Maintenance Trip Reports and Quarterly Effectiveness Evaluation Report sTime Critical Response Action for the Rocket Ridge Area of RVAAP- 04 Open Demolition Area #2, June Trip Report (#10), June 24, 2009

July 08, 2009

Final Public Involvement Plan Addendum for Rocket Ridge at Ravenna Army Ammunition Plant, 6/30/09

Final Project Work Plan for the Time Critical Removal Action (TCRA) at Rocket Ridge Area of RVAAP- 04 Open Demolition Area #2 at Ravenna Army Ammunition Plant. 6/30/09

Final Project Management Plan for the Time Critical Removal Action (TCRA) at the Rocket Ridge Area of RVAAP-04 Open Demolition Area #2 at Ravenna Army Ammunition Plant, 6/30/09

Final Remedial Design for RVAAP- 16 Fuze and Booster Quarry Landfill Ponds at Ravenna Army Ammunition Plant, 6/26/09

Final Position Paper for the Application and Use of Facility-Wide Human Health Cleanup Goals, 6/1/09

Radiation Survey Report No. CESWT-SO-R2-05-98 Monazite AOC at Ravenna Army Ammunition Plant, 5/18/98

June 26, 2009

Final Facility-Wide Groundwater Monitoring Program Report on the October 2008 Sampling Event at Ravenna Army Ammunition Plant, June 15, 2009

Draft of the Facility-Wide Groundwater Monitoring Program Report on the January 2009 Sampling Event, May 15, 2009

June 18, 2009

Operations and Maintenance Trip Reports and Quarterly Effectiveness Evaluation Report (#3) Time Critical Response Action for the Rocket Ridge Area of RVAAP- 04 Open Demolition Area #2, May Trip Report (#9), May 27, 2009

Draft Work Plan Performance-Based Acquisition for Environmental Investigation and Remediation MEC Avoidance/Removal Services, May 21, 2009

Draft Explosive Siting Plan 2008 Performance-Based Acquisition for Environmental Investigation and Remediation MEC Avoidance/Removal Services, May 21, 2009

Final Data Quality Objectives for the RVAAP- 28 Mustard Agent Burial Site at Ravenna Army Ammunition Plant, Version 1.0, May 11, 2009

May 7, 2009

Operations and Maintenance Trip Reports and Quarterly Effectiveness Evaluation Report sTime Critical Response Action for the Rocket Ridge Area of RVAAP- 04 Open Demolition Area #2, April Trip Report (#8), Apr 28, 2009

Draft Ravenna Army Ammunition Plan Installation Action Plan for FY 2009, Issue April 20. 2009

Draft Facility-Wide Human Health Cleanup Goals for Ravenna Army Ammunition Plan, Sept. 19, 2008

Final Remedial Action Completion Report for the Remediation of Soils and Dry Sediments at RVAAP- 08 Load Line 1, RVAAP- 09 Load Line 2, RVAAP- 10 Load Line 3, and RVAAP- 11 Load Line 4 at Ravenna Army Ammunition Plant, June 30, 2008

Final of the Time Critical Response Action Plan for the Rocket Ridge Area at RVAAP-04 Open Demolition Area #2, Mar. 1, 2008


Apr 30, 2009

Draft Sampling and Analysis Plan for the Remedial Investigation of RVAAP- 67 Facility-wide Sewers Addendum No. 1 at Ravenna Army Ammunition Plant, Apr 24, 2009

Final Record of Decision for Soil and Dry Sediment at RVAAP- 49 Central Burn Pits at Ravenna Army Ammunition Plant, Apr 21, 2009

Final Sampling and Analysis Plan for Groundwater Sampling at RVAAP- 12 Load Line 12 at Ravenna Army Ammunition Plant, Addendum 1, Apr 14, 2009

Apr 14, 2009 Operations and Maintenance Trip Reports and Quarterly Effectiveness Evaluation Report sTime Critical Response Action for the Rocket Ridge Area of RVAAP- 04 Open Demolition Area #2, March Trip Report (#7), Mar, 25, 2009
Mar 31, 2009

Final Record of Decision for Soil and Dry Sediment for RVAAP- 01 Ramsdell Quarry Landfill at Ravenna Army Ammunition Plant. Mar 24, 2009

Final Record of Decision for Soil and Dry Sediment for RVAAP- 12 Load Line 12 at Ravenna Army Ammunition Plant. Mar 20, 2009

Draft Data Quality Objectives for the RVAAP- 28 Mustard Agent Burial Site at Ravenna Army Ammunition Plant, Version 1.0. Mar 11, 2009

Final Facility-Wide Groundwater Monitoring Program Report on the July 2008 Sampling Event, Volume 1-6, Feb. 12, 2009

Final Revised Operations and Maintenance Plan Sand Creek Barrier System, Time Critical Response Action Rocket Ridge Area of RVAAP- 04 Open Demolition Area #2, Site-Specific Health and Safety Plan, Aug 7, 2008

Final Revised Operations and Maintenance Plan Sand Creek Barrier System, Time Critical Response Action Rocket Ridge Area of RVAAP- 04 Open Demolition Area #2, Explosive Site Plan, Aug 7, 2008

Final Revised Operations and Maintenance Plan for the Sand Creek Barrier System, the Time Critical Response Action at the Rocket Ridge Area of RVAAP- 04 Open Demolition Area #2, Military Munitions Response Program, Aug 7, 2008

Final Project Coordination Plan for the Sampling of Soils Below Floor Slabs at RVAAP- 09, 10, and 11 Load Lines 2, 3, and 4 and excavation and Transportation of Contaminated Soils to RVAAP- 11 Load Line 4 (Buildings G-1, G-1A and G-3),
Mar 13, 2008

Final Facility-Wide Groundwater Monitoring Program Report on the April 2007 Sampling Event. Nov 27, 2007.

 

Mar. 26, 2009

Final Remedial Design/Removal Action Plan for RVAAP- 34 Sand Creek Disposal Road Landfill at Ravenna Army Ammunition Plant 3/21/2004

Feb. 19, 2009 Final Remedial Action work Plan for RVAAP-05 Winklepeck Burning Grounds at Ravenna Army Ammunition Plant, July 27, 2008
Feb. 9, 2009

Draft PBA 2008 Suppliemental Investigation Sampling and Analysis Plan Addendum No. 1, Feb 4, 2009

Draft Work Plan for the Disposal of Discarded Munitions Debris & Components; Demolition of RVAAP- 35 Building 1037 - Laundry Waste Water Sump and Laundry Flame Proofing Building, and Evaluation and Recommendations for Closure of Clean-Hard Fill Sites, Jan. 26, 2009

Draft Accident Prevention Plan Disposal of Discarded Munitions Debris and Components; Demolition of RVAAP- 35 Bldg 1037 - Laundry Waste Water Sump and Laundry Flame Proofing Bldg; and Evaluation and Recommendation for Closure of Clean-Hard Fill Sites, Jan. 26, 2009

Final Work Plan for the Removal of Buildings and Concrete Floor Slabs at RVAAP- 08 Load Line 1 and Other Miscellaneous Buildings and Removal and Disposal of Pallets at Ravenna Army Ammunition Plant, Jan 16, 2009

Final Accident Prevention Plan for the Removal of Buildings and Concrete Floor Slabs at RVAAP- 08 Load Line 1 and Other Miscellaneous Buildings and Removal & Disposal of Pallets at Ravenna Army Ammunition Plant, Jan 16, 2009

Draft Sampling and Analysis Plan for Groundwater Sampling at RVAAP- 12 Load Line 12 at Ravenna Army Ammunition Plant, Addendum 1, Jan. 16, 2009

Draft Facility-Wide Groundwater Monitoring Program Report on the October 2008 Sampling Event at Ravenna Army Ammunition Plant, Jan 30, 2009

Final Project completion Report for the Munitions Response for Demolition of Load Lines 5, 7, Building 1039, and Transite Removal at Building T-1604, Removal of Remaining Concrete and Miscellaneous Debris at Load Lines 6, 9 and 11. Dec. 13, 2007

 

 

Jan, 12, 2009

Operations and Maintenance Trip Reports and Quarterly Effectiveness Evaluation Reports Time Critical Response Action for the Rocket Ridge Area of RVAAP- 04 Open Demolition Area #2, November Trip Report (#4), Nov 19, 2008

Report on the Field Survey of Concrete Monuments at Ravenna Army Arsenal, Jan 6, 1999

Jan, 9, 2009

Operations and Maintenance Trip Reports and Quarterly Effectiveness Evaluation Reports Time Critical Response Action for the Rocket Ridge Area of RVAAP- 04 Open Demolition Area #2, December Trip Report (#5), Dec. 16, 2008

Draft Facility-Wide Groundwater Monitoring Program Annual Report for 2008, Dec. 12, 2008

Final Archives Search Report for Ravenna Army Ammunition Plant, Jun. 1, 2004

Jan, 5, 2009

Final Sampling and Analysis Plan Addendum No. 1 for the Deep Bedrock Well Installation in the Basal Sharon Conglomerate. 12/19/2008

Final Project Management Plan for the 2008 Performance-Based Acquisition of Environmental Investigation and Remediation. 12/19/2008

Final Removal Action Report for the RVAAP- 49 Central Burn Pits, Dec. 05, 2008

Draft of the Multi-Increment Sampling and Analysis of Soils Below Floor Slabs at RVAAP- 09 Load Line 2, RVAAP- 10 Load Line 3, and RVAAP- 11 Load Line 4 at Ravenna Army Ammunition Plant, Dec. 4, 2008

Draft of the Sampling and Screening Analysis of Soils Below Floor Slabs at RVAAP- 09 Load Lines 2, RVAAP- 10 Load Line 3, and RVAAP- 11 Load Line 4, Version 2.0, at Ravenna Army Ammunition Plant, Dec. 01. 2008

Draft Work Plan Addendum 1 for the Sampling of Soils Below Floor Slabs and Remediation at RVAAP- 08 Load Line 1 and Other Building Locations at Ravenna Army Ammunition Plant, Nov. 18, 2008

Final Contractor Quality Control Plan for the Remedial Action at RVAAP- 05 Winklepeck Burning Grounds at Ravenna Army Ammunition Plant, Nov. 17, 2008

Final Facility-Wide Groundwater Monitoring Program Report on the April 2008 Sampling Event, Nov. 10, 2008

Draft Accident Prevention Plan for the Removal of Buildings and Concrete Floor Slabs at RVAAP- 08 Load Line 1 and Other Miscellaneous Buildings and Removal and Disposal of Pallets at Ravenna Army Ammunition Plant, Nov. 1, 2008

Draft of the Facility-Wide Groundwater Monitoring Program Report on the July 2008 Sampling Event, Volume 1-6, Oct. 31, 2008

Final Facility-Wide Groundwater Monitoring Program Background Calculation Update, Oct 28, 2008

Final Quality Assurance Project Plan Part II Addendum of the MEC Clearance and Munitions Response for RVAAP- 05 Winklepeck Burning Grounds at Ravenna Army Ammunition Plant, Oct. 27. 2008

Final Field Sampling and Analysis Plan MEC Clearance and Munitions Response Amendment 1 for RVAAP- 05 Winklepeck Burning Grounds at Ravenna Army Ammunition Plant, Oct. 24, 2008

Operations and Maintenance Trip Reports and Quarterly Effectiveness Evaluation Reports Time Critical Response Action for the Rocket Ridge Area of RVAAP- 04 Open Demolition Area #2, OctoberTrip Report, Oct. 23, 2008

Final Explosives Safety Submission for the Munitions and Explosives of Concern Survey and Munitions Response of RVAAP- 05 Winklepeck Burning Grounds at Ravenna Army Ammunition Plant, Revision 3, Amendment 3, Oct. 9, 2008

Final Site Safety and Health Plan Amendment for the Phase II MEC Clearance and Munition Response at RVAAP- 05 Winklepeck Burning Grounds at Ravenna Army Ammunition Plant, Sept. 04, 2008

Final Project Management Plan for RVAAP- 05 Winklepeck Burning Grounds Remedial Design/Remedial Action, Revision 2, Sept. 4, 2008

Final Phase I Remedial Investigation Report for RVAAP-03 Demolition Area #1 at Ravenna Army Ammunition Plant, Dec, 2001

Dec. 5, 2008 Proposed Plan for the Soil and Dry Sediment at the RVAAP-49 Central Burn Pits

Oct. 29, 2008

Final Record of Decision for Soil and Dry Sediment at RVAAP- 05 Winklepeck Burning Grounds at Ravenna Army Ammunition Plant, Aug. 6, 2008

Documents Summarizing Ammunition Production at Ravenna Arsenal between 1941 - 1974, Jan. 1, 1974

Oct. 24, 2008

Draft Project Management Plan for the 2008 Performance-Based Acquisition of Environmental Investigation and Remediation at Ravenna Army Ammunition Plant, Oct 10, 2008

Draft Site-Specific Work Plan for the RVAAP- 08 Load Line 1 Igniter Tube Disposal at Ravenna Army Ammunition Plant, Oct 2, 2008

Final Construction Completion Report Time Critical Response Action for the Rocket Area of RVAAP- 04 Open Demolition Area #2 Military Munitions Response Program, Sept. 23, 2008

Final Quality Assurance Surveillance Plan for the 2008 Performance-Based Acquisition of Environmental Investigation and Remediation at Ravenna Army Ammunition Plant, Sept, 18, 2008

Final Facility-Wide Groundwater Monitoring Program Background Calculation Update, Sept, 12, 2008

Draft-Proposed Plan for Soil And Dry Sediment at the RVAAP-49 Central Burn Pits. September 8, 2008

Final Project Management Plan for RVAAP-05 Winklepeck Burning Grounds Remedial Design/Remedial Action, Revision 2, Sept 4 2008

Draft Site Safety and Health Plan Amendment for the Phase II MEC Clearance and Munition Response at RVAAP- 05 Winklepeck Burning Grounds at Ravenna Army Ammunition Plant, Sept 4, 2008

Draft Sampling and Analysis Plan Addendum No.1 for the Deep Bedrock Well Installation in the Basal Sharon Conglomerate-8/28/08

Final of the Facility-Wide Groundwater Monitoring Program Report of the January 2008 Sampling Event, Main Text and Appendices A-C, Volume 1-3, Aug. 22, 2008

Sept. 16, 2008

Draft-Proposed Plan for Soil And Dry Sediment at the RVAAP-49 Central Burn Pits. September 8, 2008

Draft Sampling and Analysis Plan Addendum No.1 for the Deep Bedrock Well Installation in the Basal Sharon Conglomerate-8/28/08

Draft Quality Assurance Surveillance Plan for the 2008 Performance-Based Acquisition of Environmental Investigation and Remediation at Ravenna Army Ammunition Plant

August 7, 2008

Ravenna Army Ammunition Plant Deliverable Document Format Guidelines, Version 7.0, Aug. 2008

Draft Construction Completion Report Time Critical Response Action for the Rocket Area of RVAAP- 04 Open Demolition Area #2 Military Munitions Response Program, Aug. 2008

Draft Facility-Wide Groundwater Monitoring Program Report on the April 2008 Sampling Event, Volume 1 Main Text and Appendices A - D, July 2008

Draft Record of Decision for Soil and Dry Sediment at RVAAP- 05 Winklepeck Burning Grounds at Ravenna Army Ammunition Plant, July 2008


August 4, 2008

Draft Remedial Action Work Plan for RVAAP- 05 Winklepeck Burning Grounds at Ravenna Army Ammunition Plant, July 2008

Draft Facility-Wide Groundwater Monitoring Program Background Calculation Update, June 2008

Final Remedial Investigation Report Addendum No. 1 for the RVAAP- 49 Central Burn Pits at Ravenna Army Ammunition Plant, June 2008

June 24, 2008

Draft Revised Operations and Maintenance Plan Sand Creek Barrier System, Time Critical Response Action Rocket Ridge Area of RVAAP- 04 Open Demolition Area #2, Site-Specific Health and Safety Plan, May 30, 2008

Draft Revised Operations and Maintenance Plan Sand Creek Barrier System, Time Critical Response Action Rocket Ridge Area of RVAAP- 04 Open Demolition Area #2, Explosive Site Plan, May 30, 2008

Draft Revised Operations and Maintenance Plan for the Sand Creek Barrier System, the Time Critical Response Action at the Rocket Ridge Area of RVAAP- 04 Open Demolition Area #2, Military Munitions Response Program, May 30, 2008

Final of the Work Plan for the Sampling of Soils Below Floor Slabs at Load Lines 2-4 and Excavation and Transportation of Contaminated Soils to Load Line 4 (Buildings G-1, G-1A, and G-3), May 29, 2008

Final Report on the Geophysical Investigation of RVAAP-28 the Suspected Mustard Agent Burial Site. May 21, 2008

June 12, 2008 Final Report on the Geophysical Investigation of RVAAP-28 the Suspected Mustard Agent Burial Site. May 21, 2008
June 5, 2008

RVAAP Site Tour Agenda - 1968

May 15, 2008

Final Site Inspection for the Military Munitions Response Program, May 2008

RVAAP’s Facility Wide Human Health Risk Assessor Manual Amendment 1. 01 Dec 2005

May 13, 2008

Draft of the Facility-Wide Groundwater Monitoring Program Report of the January 2008 Sampling Event, Main Text and Appendices A-C, Volume 1-3, May 2008

Final Report for the Phase I Remedial Investigation at RVAAP-42 Load Line 9, Volume 1-4, Oct 2007

Final Report for the Phase I Remedial Investigation of RVAAP-33 Load Line 6, Volume 1- 4, Aug 2007

May 12, 2008

Draft of the Preliminary Evaluation of Pre (Floor Slab Removal) Contamination Beneath Selected Buildings at Load Lines 2, 3, and 4, Apr 2008

Final Facility-Wide Groundwater Monitoring Program Report on the October 2007 Sampling Event, Volume 1 – Main Text and Appendices A-C, Apr 2008

May 9, 2008

Draft Report on the Geophysical Investigation of the suspected RVAAP-28 Mustard Agent Burial Site, Feb 2008

Draft Facility-Wide Human Health Cleanup Goal White Paper, Feb 2008

Draft Report on the Geophysical Investigation of the suspected RVAAP-28 Mustard Agent Burial Site, Feb 2008

Draft of the Work Plan for the Sampling of Soils Below Floor Slabs at Load Lines 2-4 and Excavation and Transportation of Contaminated Soils to Load Line 4 (Buildings G-1, G-1A, and G-3), Apr 2008

Draft Remedial Investigation Report Addendum No. 1 for the RVAAP- 49 Central Burn Pits, Apr 2008

Final Removal Action Work Plan for RVAAP-49 Central Burn Pits, Aug 2007

Final Safety, Health and Emergency Response Plan Addendum for the Remediation of Soils at Load Lines 1, 2, 3, and 4, June 2007

Final Sampling and Analysis Plan Addendum No. 2 for the Phase I Remedial Investigation of Ramsdell Quarry Landfill, June 2006

Final Report on the Additional Groundwater Monitoring Well Installation and Groundwater Sampling at the Suspected RVAAP-28 Mustard Agent Burial Site, May 2006

Final Facility Wide Groundwater Monitoring Program Report on the May 2006 Sampling Event, Oct 2006

Final Facility Wide Groundwater Monitoring Program Report on the April 2005 Sampling Event, Aug 2005

Final Phase I Remedial Investigation December 2004 Follow-On Groundwater Sampling at RVAAP-01 Ramsdell Quarry Landfill, June 2005

Final Site Safety and Health Plan for the Phase II MEC Clearance and Munitions Response at RVAAP-05 Winklepeck Burning Grounds, Mar. 2005

Final Work Plan for Phase II MEC Clearance and Munitions Response at RVAAP-05 Winklepeck Burning Grounds, Mar. 2005

Revised Final Focused Feasibility Study for RVAAP-05 Winklepeck Burning Grounds, Mar, 2005

Final Phase I MEC Density Survey After Action Report at RVAAP-05 Winklepeck Burning Grounds, Mar, 2005

Final Facility Wide Groundwater Monitoring Program Annual Report for 2005

Final Facility Wide Groundwater Monitoring Program Report on the July 2005 Sampling Event-Main Report and Appendices A-C, Nov 2005

Final Work Plan and Sampling and Analysis Addenda for the Groundwater Monitoring Well Installation and Groundwater Sampling at the Suspected RVAAP-28 Mustard Agent Burial Site, Nov 2004

Final Proposed Remedial Goal Options for Soil at RVAAP- 08, 09, 10, and 11 Load Lines 1- 4, Sept. 2004

Final Report for the Assessment of Potential Contamination at the DLA Outdoor Storage Areas, Aug, 2003

Final Site Safety and Health Plan Addendum No. 1 for the Phase II Remedial Investigation of RVAAP-12 Load Line 12, Sept, 2000

Draft Sampling and Analysis Plan and Site Safety and Health Plan Addendum No. 2 for the Biological Measurements at RVAAP-05 Winklepeck Burning Grounds, May 2000

Final Site Safety and Health Plan Addendum No. 1 for the Phase I Remedial Investigation of Demolition Area #1, Oct 1999

May 1, 2008 Final Remedial Action Work Plan Remediation of Soils at Load Lines 1- 4  (RVAAP- 08, 09, 10, and 11) 4/5/2007

Apr. 4, 2008 Final Characterization of 14 AOCs at Ravenna Army Ammunition Plant, March 2007.

Mar. 06, 2008

Final Construction Completion Report, Munitions Response for the Demolition of RVAAP-41 Load Line 8 and RVAAP-43 Load Line 10, Addendum 1 Demolition of Building 1034, Mar. 2008

Draft Project Coordination Plan for the Sampling of Soils Below Floor Slabs at RVAAP- 09, 10, and 11 Load Lines 2, 3, and 4 and excavation and Transportation of Contaminated Soils to RVAAP- 11 Load Line 4 (Buildings G-1, G-1A and G-3),
Mar. 2008

Final Letter Report Work Plan for the Sampling of Soils Below Floor Slabs at RVAAP- 09, 10, and 11 Load Lines 2, 3, and 4 and Excavation and Transportation of Contaminated Soils to RVAAP- 11 Load Line 4 (Buildings G-1, G-1A and G-3) Feb.2008

Draft Letter Report Work Plan for Pre-Slab Removal Tasks, Jan. 25, 2008

Feb. 12, 2008

Final Record of Decision for Soil and Dry Sediment at the RVAAP-02 Erie Burning Grounds, Sept 19, 2007

Final Record of Decision for Soil and Dry Sediment at the RVAAP-04 Open Demolition Area #2, Sept 19, 2007

Final Record of Decision for Soil and Dry Sediment at the RVAAP-16 Fuze and Booster Quarry Landfill/Ponds, Sept 19, 2007

Jan. 25, 2008 Final Revised Interim Record of Decision for the Remediation of Soils at RVAAP-08, 09, 10, 11 Load Lines 1 – 4, Jan.18, 2007

Jan. 16, 2008 Installation Action Plan for Ravenna Army Ammunition Plant. FY 2007, January, 2008

Sept. 27 , 2007 Hazardous and Medical Waste Study No. 37-EF-5360-99 Relative Risk Site Evaluation for Newly Added Sites. October 1998

Aug. 31, 2007

Closure, Completion of Closure for RVAAP-14 Load Line 6 Evaporation Unit. January 1993

Closure, Completion of Partial Closure of RVAAP-07 Building 1601 Hazardous Waste Storage and RVAAP-05 Winklepeck Burning Grounds (OBG). May 1999

Closure, Final Closure Inspection of RVAAP-01 Ramsdell Quarry Landfill. Sept. 1990

Closure, Final Closure Report Approval for Buildings W-221 and X-232. July 2000

Closure, Final Closure Report for RVAAP-37 Pesticide Storage Building T-4452. Sept. 2000

Closure, No Further Action for RVAAP-27 Building 854-PCB Storage. Sept. 1999

Closure, No Further Action, Statement of Basis for the Final Decision for RVAAP-47 Building T-5301 Interim Removal Action. Dec. 2000

July 25, 2007

Draft Facility-Wide Groundwater Monitoring Program Report on the April 2007 Sampling Event. July 16, 2007.

 

July 18, 2007

Final Stormwater Pollution Prevention Plan Remediation of Soils at RVAAP-08, 09, 10, and 11, Load Lines 1-4. July 12, 2007. Shaw.

 

July 09, 2007

Final Facility-wide Groundwater Monitoring Program Report on the January 2007 Sampling Event (Sample Event No. 1). July 9, 2007. SpecPro Inc.

 

June 26, 2007

Draft Removal Action Work Plan for Central Burn Pits (RVAAP-49), Ravenna Army Ammunition Plant, Ravenna, Ohio. June

Final Action Memorandum for Central Burn Pits (RVAAP-49, Ravenna Army Ammunition Plant, Ravenna, Ohio. June 2007


June 20, 2007

Draft Report for the Remedial Investigation at Load Line 6 (RVAAP–33) at the Ravenna Army Ammunition Plant. June 2007

Draft Report for the Remedial Investigation at Load Line 9 (RVAAP–42) at the Ravenna Army Ammunition Plant. May 2007


Apr. 02, 2007

Final Proposed Plan for Soil and Dry Sediment at Fuze and Booster Quarry Landfill/Ponds (RVAAP-16) Ravenna Army Ammunition Plant, Ravenna, Ohio. March 2007.

Final Proposed Plan for Soil and Dry Sediment at the Ramsdell Quarry Landfill (RVAAP-01) Ravenna Army Ammunition Plant, Ravenna, Ohio. March 2007

Final Proposed Plan for Soil and Dry Sediment at Load Line 12 (RVAAP-12) Ravenna Army Ammunition Plant, Ravenna, Ohio. March 2007

Final Facility-Wide Groundwater Monitoring Program Plan For The Ravenna Army Ammunition Plant Ravenna, Ohio. September 2004



Mar. 20, 2007 Public Presentation for Proposed Plans at Erie Burning Grounds and Open Demolition Area #2, March 13, 2007
Feb. 27, 2007 Final Proposed Plan for Soil and Dry Sediment at Open Demolition Area #2 (RVAAP- 04) Ravenna Army Ammunition Plant Ravenna, Ohio February 2007
Feb. 27, 2007 Final Proposed Plan for Soil and Dry Sediment at Erie Burning Grounds (RVAAP-02) Ravenna Army Ammunition Plant Ravenna, Ohio February 2007
Jan. 31, 2007 Final Engineering Evaluation/Cost Analysis for Central Burn Pits (RVAAP-49) Ravenna Army Ammunition Plant, Ravenna, Ohio, January 2007
Jan. 19, 2007 Final Focused Feasibility Study for the Remediation of Soils at LLs 1-4, RVAAP May 2005

Final Phase II Remedial Investigation at the Upper and Lower Cobbs Pond (AOC 29) September 2005

Final Report Interim Removal Action at Load Line 11 (AOC-44) March 2004

Final Remedial Investigation at Load Line 11 (AOC-44) September 2005

Final Report for Remedial Design/Removal Action at Paris-Windham Road Dump (AOC-51) at RVAAP March 2004

Final Sampling and Analysis Plan Addendum for the Characterization of 14 RVAAP AOCs at RVAAP Oct. 2004

 

Nov. 8, 2006

Ravanna Army Ammunition Plant Director's Final Findings and Orders

Final Facility-Wide Groundwater Monitoring Program Plan For The Ravenna Army Ammunition Plant Ravenna, Ohio. September 2004


Oct. 31, 2006

Revised Final Feasibility Study for Ramsdell Quarry Landfill (RVAAP-01), Ravenna Army Ammunition Plant, Ravenna, Ohio, October 2006


Sept. 29, 2006

Final Addendum to the Phase II Remedial Investigation Report for Erie Burning Grounds (RVAAP-02) Ravenna Army Ammunition Plant Ravenna, Ohio. September 2006


Sept. 15, 2006 Revised Final Report On The Biological Field-Truthing Effort At Winklepeck Burning Grounds At Ravenna Army Ammunition Plant, Ravenna, Ohio. August 2006
Sept. 13, 2006 Final Addendum to the Phase II Remedial Investigation Report for Open Demolition Area #2 (RVAAP-04) Ravenna Army Ammunition Plant Ravenna, Ohio. September 2006.
July 27, 2006

Draft Addendum to the Phase II Remedial Investigation Report for Erie Burning Grounds (RVAAP-02) Ravenna Army Ammunition Plant Ravenna, Ohio. July 2006.

Draft Addendum to the Phase II Remedial Investigation Report for Open Demolition Area #2 (RVAAP-04) Ravenna Army Ammunition Plant Ravenna, Ohio. July 2006


July 21, 2006

Final Feasibility Study for Fuze and Booster Quarry Landfill/Ponds (RVAAP-16) Ravenna Army Ammunition Plant Ravenna, Ohio July 2006


July 17, 2006

Final Feasibility Study for Ramsdell Quarry Landfill (RVAAP-01) Ravenna Army Ammunition Plant Ravenna, Ohio July 2006
(see revised document, Oct. 31, 2006)

Final Feasibility Study for Load Line 12 (RVAAP-12) Ravenna Army Ammunition Plant Ravenna, Ohio July 2006

 

April 7, 2006

Final Phase II Remedial Investigation Report for the Open Demolition Area #2 (RVAAP-04) at the Ravenna Army Ammunition Plant Ravenna, Ohio September 2005


April 4, 2006

Draft Feasibility Study for Ramsdell Quarry Landfill (RVAAP-01) Ravenna Army Ammunition Plant Ravenna, Ohio March 2006 (replaced by Final Version, July 17, 2006)

Draft Feasibility Study for Erie Burning Grounds (RVAAP-02) Ravenna Army Ammunition Plant Ravenna, Ohio March 2006

Draft Feasibility Study for Open Demolition Area #2 (RVAAP-04) Ravenna Army Ammunition Plant Ravenna, Ohio March 2006

Draft Feasibility Study for Load Line 12 (RVAAP-12) Ravenna Army Ammunition Plant Ravenna, Ohio March 2006
(replaced by Final Version, July 17, 2006)

Draft Feasibility Study for Fuze and Booster Quarry Landfill/Ponds (RVAAP-16) Ravenna Army Ammunition Plant Ravenna, Ohio March 2006 (replaced by Final Version, July 21, 2006)

Draft Feasibility Study for Central Burn Pits (RVAAP-49) Ravenna Army Ammunition Plant Ravenna, Ohio March 2006

Final Facility-Wide Biological and Water Quality Study 2003 Ravenna Army Ammunition Plant November 2005

Final Phase II Remedial Investigation Supplemental Report for Load Line 12 (Rvaap-12) at the Ravenna Army Ammunition Plant, Ravenna, Ohio November 2005

Final Phase I/Phase II Remedial Investigation of the Fuze and Booster Quarry Landfill/Ponds (RVAAP-16) Ravenna Army Ammunition Plant Ravenna, Ohio November 2005

Final Phase I Remedial Investigation Report for Ramsdell Quarry Landfill at the Ravenna Army Ammunition Plant, Ravenna, Ohio September 2005

Final Phase II Remedial Investigation Report for Erie Burning Grounds (Rvaap-02) at the Ravenna Army Ammunition Plant, Ravenna, Ohio September 2005

Final Remedial Investigation Report for the Central Burn Pits (Rvaap-49) at the Ravenna Army Ammunition Plant Ravenna, Ohio September 20, 2005

   
   
   
   

 

Return to Documents